Skip to content
NOWCAST KCRA 3 News at 7am
Live Now
Advertisement

Baltimore shipping channel fully reopens after Francis Scott Key Bridge collapse

700-foot channel reopens 11 weeks after Key Bridge collapse

Baltimore shipping channel fully reopens after Francis Scott Key Bridge collapse

700-foot channel reopens 11 weeks after Key Bridge collapse

YEAH, THAT’S RIGHT, IT COULD BE THAT SOON, BECAUSE UNIFIED COMMAND SAYS THEY HAVE ALL OF THE STEEL OUT OF THE WATER. THEY ARE JUST COMPLETING THE FINAL SWEEPS WITH SONAR TO MAKE SURE THERE’S NO DEBRIS UNDER THE MUD LINE. THEY SAY IT COULD BE AS EARLY AS LATER TODAY OR TOMORROW MORNING. ONCE WE CERTIFY THE CHANNEL, WE’LL BE ABLE TO HAVE THE COAST GUARD COME OUT, MOVE THE MOVE THE BUOYS TO MARK THE CHANNEL. NEARLY 11 WEEKS AFTER THE KEY BRIDGE COLLAPSE IN THE U.S. ARMY CORPS OF ENGINEERS SAYS THE MAIN SHIPPING CHANNEL IS ALMOST READY TO REOPEN AT ITS FULL 700FT WIDE, 50FT DEEP, THAT WILL FULLY RESTORE THE BUSINESS AT THE PORT OF BALTIMORE. WE WILL MAKE SURE THAT WE ARE AS THOROUGH AND DISCIPLINED AS WE HAVE BEEN WITH EVERY HIGH SPOT, SO THAT WHEN WHENEVER WE TURN OVER A CHANNEL, IT’S SAFE FOR NAVIGATION. SINCE THE DALI SHIP WAS REMOVED, CREWS HAVE BEEN REMOVING ANY LEFTOVER STEEL IN SURVEYING BELOW THE MUDLINE AND REMOVING ANY ROADWAY AND WRECKAGE. THERE WERE THOSE PORTIONS THAT WERE STICKING UP WERE EXPLORED, AND SOMETIMES IT WAS JUST THE MUD, THE WAY THE SUCTION FROM THE BUCKET WAS LEFT BEHIND. BUT SOMETIMES WE DID PULL UP VERY LONG PIECES OF WRECKAGE THAT WERE DEEP DOWN, SOME 50FT. EVEN LATELY, EVEN UP TO 80FT LONG. IT’S A TEDIOUS PROCESS, BUT COLONEL ESTY JASON, WITH THE ARMY CORPS OF ENGINEERS SAYS THEY WANT TO MAKE ABSOLUTELY SURE THE CHANNEL IS SAFE FOR NAVIGATION BEFORE GIVING IT THE ALL CLEAR AND EVEN AFTER THEY HIT THAT MILESTONE, THEIR WORK ISN’T COMPLETELY OVER. ONCE THE CHANNEL IS OPENED AT 700FT, YOU’RE STILL GOING TO BE ABLE TO SEE OUR CONTRACTOR, DON JOHN MARINE, OUT HERE PULLING UP WRECKAGE THAT MIGHT BE BELOW THE MUD LINE THAT THEY’RE PULLING. THEY’RE GOING TO BE PULLING OUT ANY REMAINING STEEL FROM THE BRIDGE THAT IS BEHIND ANY REMAINING CONCRETE THAT’S UNDER THE MUD AS WELL. NOW, ALL OF THE CLEANUP AND SALVAGE WORK IS SCHEDULED TO BE DONE BY THE END OF THIS MONTH.
Advertisement
Baltimore shipping channel fully reopens after Francis Scott Key Bridge collapse

700-foot channel reopens 11 weeks after Key Bridge collapse

The main shipping channel into Baltimore’s port has fully reopened to its original depth and width following the March 26 collapse of the Francis Scott Key Bridge, which blocked most maritime traffic into the harbor.Video above aired before the announcement was releasedOriginal operational dimensions of 700 feet wide and 50 feet deep are restored for commercial maritime transit through the Port of Baltimore."We are proud of the unified efforts that fully reopened the federal channel to port operations," Lt. Gen. Scott Spellmon, commanding general of the U.S. Army Corps of Engineers, said in a statement released Monday evening. "The partnerships that endured through this response made this pivotal mission successful."After almost 11 weeks, officials said crews have removed all of the steel, but they were conducting final checks with sonar to ensure no more debris remained below the mudline."We will make sure that we are as thorough and disciplined as we have been with every high spot so that whenever we run over the channel, it's safe for navigation," U.S. Army Corps of Engineers Col. Estee Pinchasin, commander of the Baltimore District, told sister station WBAL-TV earlier Monday.Following the removal of wreckage at the 50-foot mudline, Unified Command performed a survey of the federal channel on Monday and certified the riverbed is safe for transit.Now, crews are going back with sonar to check out raised spots on the river bed."Those portions that were sticking up were explored. Sometimes, it was just the mud, the way the suction from the bucket was left behind, and sometimes, we did pull up very long pieces of wreckage that were deep down some 50 feet, some even up to 80 feet long," Pinchasin said. The process has taken longer than the end-of-May deadline, but the Army Corps of Engineers wants to be absolutely sure the channel is safe before turning it over. "We're scheduled to dredge this channel this coming fiscal year 2025 and we want to make sure we don't leave that kind of obstacle for the dredgers that are going to come through," Pinchasin said. The work isn't completely over; crews still need to remove wreckage outside that channel. "The Corps of Engineers is never done," Pinchasin said. "This is our channel. We maintain it all the time. We're going to, God willing, be maintaining it for many generations to come."All of the cleanup and salvage work is scheduled to be complete by the end of June.The Associated Press contributed to this report

The main shipping channel into Baltimore’s port has fully reopened to its original depth and width following the March 26 collapse of the Francis Scott Key Bridge, which blocked most maritime traffic into the harbor.

Video above aired before the announcement was released

Advertisement

Original operational dimensions of 700 feet wide and 50 feet deep are restored for commercial maritime transit through the Port of Baltimore.

"We are proud of the unified efforts that fully reopened the federal channel to port operations," Lt. Gen. Scott Spellmon, commanding general of the U.S. Army Corps of Engineers, said in a statement released Monday evening. "The partnerships that endured through this response made this pivotal mission successful."

After almost 11 weeks, officials said crews have removed all of the steel, but they were conducting final checks with sonar to ensure no more debris remained below the mudline.

"We will make sure that we are as thorough and disciplined as we have been with every high spot so that whenever we run over the channel, it's safe for navigation," U.S. Army Corps of Engineers Col. Estee Pinchasin, commander of the Baltimore District, told sister station WBAL-TV earlier Monday.

Following the removal of wreckage at the 50-foot mudline, Unified Command performed a survey of the federal channel on Monday and certified the riverbed is safe for transit.

Now, crews are going back with sonar to check out raised spots on the river bed.

"Those portions that were sticking up were explored. Sometimes, it was just the mud, the way the suction from the bucket was left behind, and sometimes, we did pull up very long pieces of wreckage that were deep down some 50 feet, some even up to 80 feet long," Pinchasin said.

The process has taken longer than the end-of-May deadline, but the Army Corps of Engineers wants to be absolutely sure the channel is safe before turning it over.

"We're scheduled to dredge this channel this coming fiscal year 2025 and we want to make sure we don't leave that kind of obstacle for the dredgers that are going to come through," Pinchasin said.

The work isn't completely over; crews still need to remove wreckage outside that channel.

"The Corps of Engineers is never done," Pinchasin said. "This is our channel. We maintain it all the time. We're going to, God willing, be maintaining it for many generations to come."

All of the cleanup and salvage work is scheduled to be complete by the end of June.

The Associated Press contributed to this report

This content is imported from Twitter. You may be able to find the same content in another format, or you may be able to find more information, at their web site.
This content is imported from Twitter. You may be able to find the same content in another format, or you may be able to find more information, at their web site.
This content is imported from Twitter. You may be able to find the same content in another format, or you may be able to find more information, at their web site.